Scope of Work
- The decommissioning and removal of the four existing units took place on first two days of the vessel docking, modifications to the existing en-gine foundations then took place ready to accept the new units
- The new generator sets weighed 3500kgs each
- Each generator was lifted down the side of the vessel and fitted in through the side shell opening previously cut for the removals
- New fuel, water cooling, air start and exhaust pipework was also in-stalled
- Electrical disconnections, installation of new cables and load bank commissioning was included in the project
- Dales Marine’s Project Manager handed over the completed project with the attending vessel Superintendent and the vessel Chief Engineer