SWING-DOWN THRUSTER EXCHANGE — PLATFORM SUPPLY VESSEL
October 2026
Location
North Sea
The Client Challenge
A platform supply vessel operating on contract in the North Sea needed a swing-down thruster exchanged in dry dock. As the vessel was under contract, minimising downtime was the priority, every day in dock was a day off-hire. Our client sent a service engineer from Norway with the replacement unit, and estimated the exchange would take 12 days.
What We Did
Dales Marine's dock blocks are set at 2.7 metres, giving enough clearance for the thruster to be deployed while the vessel was in dock, a requirement the job depended on. As soon as the vessel was dry, we lowered the thruster that evening to drain the oil, and began dismantling the existing unit the following day.
In parallel, we started removing parts from the replacement unit so it would fit the opening, and worked through water ingress in the system by flushing and cleaning the majority of the pipework. Our team worked five days and three nights to hit the completion date, finishing with full alignment checks between the motor and the new unit through the coupling.
The 10-tonne thruster unit was lifted in and out of dock using our on-site 90-tonne mobile crane, with dedicated chain blocks and skates used to manoeuvre it into position.
The Results
Our client's own service engineer estimated the exchange would take 12 days. Dales Marine completed it in 8 shifts, getting the vessel back on contract with minimal off-hire time, exactly the outcome a time-critical, contracted vessel needed.